Fire Station #2

  • Location

    East Texas Region – Pearland TX

  • Services

    Construction Management

  • Project Description

    Providing Construction Management inspection services for City of Pearland.

  • Client

    City of Pearland

  • Cost

    $3,669,000

AG|CM has been selected to work as the Construction Manager for the City of Pearland Fire Station #2 project to provide Budget/Change & Schedule Management, Quality Assurance and Management of Quality Control Inspectors.

Planned Substantial Completion walk thru on January 7, 2016 The Fire Station project is at a 90% percent the overall project has had three walk through, we are waiting on the final walk inside the building. Crain group is waiting on the Geo Teck report in order to install the east concrete wall on the premises. The pond is also at 95% percent complete some dirt work is still needed in order to be done. Crain Group has some cleanup work and fill in some ruts that were made by the sub-contractor on the neighbor’s property adjacent to the Fire station.